The School District of Palm Beach County, Florida, invites qualified Architects licensed by the State of Florida to submit a Proposal for:
DESIGN SERVICES FOR: CORE RENOVATIONS AT:
PROJECT NAME: CORAL SUNSET ELEMENTARY SCHOOL
PROJECT ADDRESS: 22400 HAMMOCK STREET, BOCA RATON, FL 33428
RFP NO.: 26C-008H
PROJECT NO.: 1811-8465
PROPOSALS SHOULD BE BASED UPON THE FOLLOWING DESCRIPTION OF WORK:
The ARCHITECT shall provide all necessary professional services to deliver Permitted Design Documents within the established Construction Budget and in accordance with the established Design Schedule.
Design services are required for the Core Expansion project at Coral Sunset Elementary School. The Design Phase will include preparing construction contract documents for the remodel and/or addition to the school to meet the District’s standard student capacity. The design services will cover the remodel, renovation, and/or building addition of core-related spaces, which may include the dining/stage area, kitchen, clinic, administration spaces, media center, restrooms, exterior corridor access, and related parking areas, with site modifications as needed.
The required deliverables include, but are not limited to: A Scope Validation Report, Statement of Probable Construction Cost, Project Schedules, Phasing of Design Plans as directed by the OWNER, Completion of permitted Construction Documents within the specified Design Schedule, Life Safety plan, updated FISH Plans, FF&E Schedule & Specifications, Design Calculations, Life Cycle Cost Analysis, Color Charts, and Finish Schedules. The ARCHITECT will be required to certify that the permitted design complies with one of the energy-efficient and sustainable building standards per F.S. 255.2575.
The Permitted Design must incorporate all requirements outlined in the Florida Building Code, Florida Accessibility Code, and State Requirements for Educational Facilities, NFPA Standards, District Master Specifications, District Design Criteria, and all other applicable specifications.
ESTABLISHED GMP CONSTRUCTION BUDGET: $3,800,000.00
DESIGN SCHEDULE BASED UPON ESTABLISHED DATES FOR AWARD OF DESIGN CONTRACT AND DESIGN NOTICE TO PROCEED:
AWARD OF DESIGN CONTRACT: FEBRUARY 18, 2026
DESIGN NOTICE TO PROCEED: FEBRUARY 27, 2026
COMPLETION OF SCHEMATIC DESIGN/SV REPORT: MARCH 27, 2026
COMPLETION OF 100% DESIGN DEVELOPMENT: MAY 27, 2026
COMPLETION OF 100% CONSTRUCTION DOCUMENTS: AUGUST 28, 2026
PERMITTED CONSTRUCTION DOCUMENTS: SEPTEMBER 28, 2026