The project consists of but is not limited to the demolition/abandonment of existing
6-inch AC waterline, service meters, and fire hydrants, salvage of appurtenances, construction of a new six
inch and eight-inch C900 PVC potable waterline between E. Homer Dr. and E. Cellini Dr. via open trench
methods including hydrants, valves, tie-ins, and appurtenances, new service lines via horizontal directional
drilling from the new main to the existing water meter pit, erosion control, earthwork, cutting and patching
and repaving of roads, and all appurtenances as specified and required for a complete and functional
system. The main waterlines will extend approximately 2,400 linear feet. All materials as indicated on the
drawings will be provided by the contractor and must be installed, along with the completion of all associated
site work relating to the new potable waterline.