This project will consist of: • Removal and re-alignment of approximately 2,500 LF of existing pathway in LaBonte Park. The existing pathway contains mostly paved surfacing. The new pathway will be constructed of concrete per the grant/spec documents. 8’ wide, 6” concrete over 6” compacted base. • Replacement of approximately 2,200 LF of existing pathway in LaBonte Park. The existing pathway contains mostly paved surfacing. The new pathway will be constructed of concrete per the grant/spec documents. 8’ wide, 6” concrete over 6” compacted base. • Installation of approximately 1,800 LF of new pathway in LaBonte Park. The new pathway will be constructed of concrete per the grant/spec documents. 8’ wide, 6” concrete over 6” compacted base. • Replacement of Curb & Gutter as needed due to damage or degradation per City Standard Specifications.