Specifications include, but are not limited to: WATER MAIN RELAYS, at the following locations: W. Vienna Ave. (WT410200645), N. 76th St. to N. 80th St. (28 working days); N. 66th St. (WT410200659), W. Congress St. to W. Medford Ave. (41 working days); N. 67th St. (WT410200660), W. Hope Ave. to W. Marion St. (17 working days); N. 67th St. (WT410200661), W. Congress St. to W. Glendale Ave. (28 working days); W. Glendale Ave. (WT410200662), N. 66th St. to N. 67th St. (7 working days); N. 69th St. (WT410200663), W. Marion St. to W. Glendale Ave. (35 working days); N. 70th St. (WT410200664), W. Capitol Dr. to W. Congress St. (46 working days); N. 71st St. (WT410200665), W. Capitol Dr. to W. Congress St. (47 working days); W. Hope Ave. (WT410200666), N. 66th St. to N. 73rd St. (39 working days). (Note: Contractor to furnish and install approximately 15,396 lin. ft. of 16”, 12”, 8”, 6”, 4” and 3” ductile iron pipe. City to furnish miscellaneous materials as shown on plans and proposal form.