Specifications include, but are not limited to: The project includes miscellaneous removals, grading, storm sewer, breaker run aggregates, concrete pavement, concrete curb and gutter, concrete sidewalk, erosion control, landscaping, traffic signal items, and incidental construction. The project will also construct an extension of the CE Trail along the north side of the roadway. ESTIMATE OF MAJOR QUANTITIES Excavation Common 18,706 CY Base Aggregate Dense, ¾-Inch 407 Tons Base Aggregate Dense, 1 ¼-Inch 15,469 Tons Breaker Run 15,857 Tons Concrete Pavement, 6-Inch 180 SY Concrete Sidewalk 5,020 SF Concrete Curb and Gutter 18-Inch Type D 414 LF Concrete Curb and Gutter 4-Inch Sloped 36-Inch Type D 3,930 LF Concrete Curb Pedestrian 48 LF Storm Sewer Pipe 12-Inch 277 LF Storm Sewer Pipe 15-Inch 471 LF Storm Sewer Pipe 18-Inch 485 LF Storm Sewer Pipe 24-Inch 328 LF Storm Sewer Pipe 36-Inch 140 LF Storm Sewer Pipe 42-Inch 123 LF Storm Sewer Structures 20 Each