Specifications include, but are not limited to: Phase I Construct relocated Harp Rd. 915 from Station 71+50 to 70+00. Maintain traffic on existing Harp Rd. 915. Construct the left lane of proposed C.R. 1 from Station 12+50 to 15+50. Construct detour road and bridge from Station 100+10 to 102+40. Utilize the existing bridge for traffic. Phase II Construct the right lane of proposed C.R. 1 from Station 12+50 to 15+50 and both lanes from Station 15+50 to 19+50, including the new bridge. Construct the Church access road from Station 50+00 to 50+75. Construct C.R. X from Station 30+00 to 31+65. Utilize detour road for traffic. Phase Ill Construct both lanes of proposed C.R. 1 from Station 10+00 to 12+50. Remove Detour road. Phase IV 1. Perform final paving, pavement markings, and signage for all the newly constructed roadways.