The purpose of amendment 1 is to answer questions and extend RFQ close date. RFQ close date is changed from 8/6/25 1PM EST to 8/15/25 1PM EST. Q.1 What is the VA measurement for the ADA ramp? A.1 See picture and measurements. Q.2 Does site require a walking area? No, foot traffic will utilize the ramp, so a foot path is not needed. Q.3 If yes, Is the ramp positioned on the left side (container side) or the right (generator side)? NA Q.4 Are there any site dimensions or required ramp lengths available? See Q.1 answer. Q.5 Can you provide elevation or slope details for the ramp location? See Q.1 answer. Q.6 Are there any drawings, site photos, or diagrams available that show the ramp area? Yes, see page 4 on SOW for pictures.