This project consists of drilling a 750-foot deep, 16-inch diameter municipal drinking water well, installing casing, and grout surface seal. 1 Premobilization Submittals, Mobilization, Demobilization, and Site Preparation 1 LS 2a Drill 24-Inch Borehole 100 LF 2b Furnish and Install 20-Inch Conductor Casing 100 LF 2c Furnish and Install Formation Cement Grout Seal 5 CY 3a Drill 20-inch Borehole 300 LF 3b Furnish and Install 16-Inch Production Casing 403 LF 3c Furnish and Install Permanent Formation Cement Grout Seal 20 CY 4 Drill Lower Borehole 350 LF 5 Well Development 1 LS 6 Furnish, Install and Remove Test Pump 1 LS 7 Perform 8-hour Step Rate Test and 72-hour Constant Rate Test 80 HR 8 Plumbness and Alignment Surveys 1 LS 9 Well Video Survey 1 LS 10 Well Disinfection 1 LS 11 Casing Stick Up 1 LS 12 Site Restoration 1 LS 13 Standby Time 24 HR