The City anticipates that the scope of work will include some or all of the following listed activities. Other related scope items not listed below may also be included. • Kickoff meeting with city project manager and other staff including a walking tour of the building/site. • Review any existing historical plans for the facility, affected utility and operational services, and its structure. • Prepare 60% and 90% plans and final PS&E package for bidding. • Prepare, submit, monitor, (amend as necessary), and complete all required permitting. • Plan construction phasing to allow for continuous plant operation within the digestor facilities during the rehabilitation work. • Coordinate with city during design to identify and design for impacts to water, sewer, electrical, gas, stormwater and other onsite utilities.