A. Project location is the Cowlitz County Administration Building at 207 Fourth Avenue N in Kelso, Washington. B. The County intends to occupy the building throughout the entire project. To minimize conflict and interactions with the public, the performance of the project on weekend days will be allowed. The contractor shall not charge additional fees for this optional weekend work. All work conducted on weekends should be included in the original bid pricing, and no separate charges for weekend work will be accepted. C. The successful contractor will have 30 days to complete the project once work has commenced. The start date will be established during the pre-construction meeting, which will take place following contract award and execution. Final completion of the project must be achieved by September 30, 2025. D. At least seventy-five percent (75%) of the work to be performed must be completed by the contractor’s own forces.