Installation of a permanent pumping system between Pond 20 and the Sturgeon Building at Neosho NFH.
Waterline Installation: Design and install a 4" waterline to transport water from Pond 20 to the existing rearing building.
Electrical Connections: Design and install electrical service for a 2 HP, 3-phase submersible pump, including connections to the existing service panel and installation of a new pump controller for variable speed control.
And all other requirements as outlined in the Scope of Work.
Site Visit: Thursday, September 4, 2025, @ 10:00 AM CST. POC: Nathan Eckert, (417)592-7400, or nathan_eckert@fws.gov
Questions Due: Friday, September 5, 2025 @ 3:00 PM EST to Bill Koski, william_koski@fws.gov
Quotes Due: Thursday, September 11, 2025 @ 3:00 PM EST to Bill Koski, william_koski@fws.gov
The Magnitude of this project is between $25,000.00 and $100,000.00.