Sealed bids are invited for the work can be generally as reshaping earthen berms at two separate petroleum training sites on Ft. Pickett. Each berm site consists of two four-sided containment berms; each of these berms are designed to hold a 210,000-gallon collapsible fabric fuel tanks [NIC]. These berms are key to establishing secondary containment for the fuel tanks at Fort Pickett, Blackstone Virginia The work can be generally described as: The work can be generally described as removing existing tarps and weed barrier, reshaping existing berms, establishing positive drainage, installing drainpipes and supplying and installing new geotextile weed barriers at each of the four berm sites on Fort Pickett, Blackstone Virginia. The work is considered to be non-capital construction.