• Remove existing asphalt. • Excavate area for base stone. • Apply 21-A stone base up to 6”. • Grade area to provide proper drainage. Play area should be generally flat with only enough slope to provide adequate drainage. • Apply 2.5” of standard asphalt base and apply 1.5” of IM-19 asphalt mix with compaction. Owner is aware of the heavy duty nature of this mix. Potential future use of the play area as a bus lot is possible. • Apply line striping for two basketball courts. • Approximate area to be paved is 14,800 square feet. Contractors must confirm area with their own measurements as 14,800 square feet is an approximation of the actual area to be paved. • Any required permits are the responsibility of the proposer. • Work to be started after 6/1/24 and completed by 8/1/24. A financial penalty of .5% of the total price may be imposed for each day work is not completed beyond 8/1/24. • Proposal should include an executable contract which contains all terms, conditions, specifications, and scope contained in this RFP.