Specifications include, but are not limited to: The scope of work will include tearing down the existing sand shed, saving and reusing the existing roof trusses, and reconstructing the Sand Shed to specifications set by the following specifications: - Contractor will be responsible for all excavating - Excavating – top of new foundation 1’ above existing grade - Existing roof trusses will be reused - Reuse as much of existing standing seem roof as possible - There is 1 street light on the outside of the building a spot light and an outlet on the inside of the building that will need to be disconnected. New electrical to match existing. - 4’ underground cement frost wall, including footings, as shown on plan - 8’ above grade cement wall with buttresses, as shown on plan - 30’ X 100’ slab, sloping 1/8” per foot towards opening, as shown on plan - 10’ 2 X 6 wall on top of 8’ cement wall, as shown on plan - All demolition material to be removed from site by contractor.