Specifications include, but are not limited to: Project Intent: To elevate the existing single story wood framed building so that the top of the first floor will be at or above the base flood elevation. The top of the existing first floor is at El. 1133.84’. The top of the proposed elevated first floor is at El. 1136.90’. The base flood elevation (BFE) at this site is 1136.5’. Installing any required temporary bracing of wood superstructure, disconnecting the existing electrical and plumbing utilities and any exterior attachments (decks, stairs, etc), modifying existing foundation as required to install lifting hardware and installing the required supports to temporarily support the building. o removing any remaining wood framing from the existing foundation, installing vertical reinforcing at all building corners and at 4’-0” o.c., filling existing cores where vertical reinforcing has been installed with 3000 psi sand and cement grout.