Specifications include, but are not limited to: Santaquin City anticipates a base bid that includes a 2” asphalt overlay of 400 South, 100 West, & 550 South, preparing for and the placement of concrete and asphalt along the east side of 300 West, and pulverizing the existing asphalt, regrading, installing new road base, and paving Center Street. The Additive Alternates include the placing of curb and gutter and constructing the additional roadway of Center Street, including storm drainage improvements. Any of the Additive Alternates identified in “Exhibit A” 2020 Road Projects may be added to the contract as/if Bid unit pricing and funding may allow and only as directed and authorized by the Santaquin City Public Works Director and the City Engineer.