Specifications include, but are not limited to: 1. We need to hire a contractor to tear out small shed, pump, and plastic water tank. The shed is approximately 8X10, and all the electrical and other equipment for the pump sit within the shed. The shed sits on top of the underground plastic tank (maybe 1000 gallon tank). 2. We need a contractor to install at least a 1000 gallon cement vault in the ground 3. We need a contractor to install a small shed on top of the vault 4. We need a contractor to install a new pressurized well pump (including electrical work that meets code). Electrical is already in the small building, it doesn’t have to be pulled from anywhere 5. We need a contractor to install new PVC pipe from the well head to the vault. 6. Finally, the vault overflow should connect to the PVC pipe we have buried in the ground already that feeds the small wetland pond.