Specifications include, but are not limited to: 1. The damaged grade beam is to be cleaned, removing all debris and loose concrete material; 2. Two (2) piers are to be installed for this foundation repair as shown on the attached drawing; 3. The exposed cable is to be removed and replaced with a new cable of the same size and material properties; 4. The concrete voids in the grade beam which exist are to be filled with an epoxy concrete grout material, equal to or better than “Sika Top - 123Plus” or SAHA approved equal (see attached specifications). 5. After the concrete grout material has set with sufficient time to gain the needed compressive strength (about seven (7) days), the cable is to be tensioned to the required strength; and, 6. The excavation is to be backfilled and the site is to be returned to its original condition.