Specifications include, but are not limited to: The Contractor shall supply their own HDPE fusion machine and have technicians to operate it and install the pipe. The following material will be needed. 4.1.1 950FT of 6” IPS SDR17 pipe PE4710; AWWA C906 Standard 4.1.2 Five (5) 6” Flanged Gate Valves 4.1.3 Two (2) 6” IPS SDR17 Tees. 4.1.4 One (1) 6” IPS SDR17 90 Degree ELLS. 4.1.5 Two (2) 6” IPS SDR17 Flange Adapters 4.1.6 Two (2) 6” IPS 150psi DR11/DR17 Convoluted Back-up Tings. 4.2 The Contractor shall provide the Contract Manager and/or designee with the project schedule five days prior to commencing work. 4.2.1 The contractor shall adhere to work hours of Monday through Friday, 6:00 a.m.- 2:30 p.m. Anything past 2:30 p.m. would need prior approval from the Contract Manager and/or designee.