Specifications include, but are not limited to: New Administration Building – PHASE I •Existing 16 acres site on Avenue I across from the Lamar CISD Traylor Stadium •Site Improvements •90,000 SF 2-story building Project Construction Budget including Cost of Work, General Conditions Fee & CM Fee: •Approximately $30,900,000.00 Schedule: •GMP documents –September 15, 2024 (80% CDs) •Award of GMP #1 – November 19, 2024 •Start of construction – November 20, 2024 •Anticipated substantial completion May 1, 2026 •Special schedule considerations: Project is intended for use on June 1, 2026 Brazos Crossing Renovations– PHASE II •Existing 54,000 SF 2-story building at 3911 Avenue I. •Renovations will provide space for the Technology Department Offices and the Lamar CISD Police Stations. •Site Improvements Project Construction Budget including Cost of Work, General Conditions Fee & CM Fee: •Approximately $6,100,000.00