The following is a general list of tasks that are to be performed by the successful CMAR. Construction Schedule Development 1. CMAR will provide critical information and assist in the development of a Master Construction Schedule. The project schedule will identify all critical milestones beginning with Mobilization and ending with Close-out. The schedule will identify any temporary construction/protection/utilities/temporary road & lane closures to support the adjacent facilities to remain in use and access during the construction process. Public and Franchise utility installations, relocations, cut over’s, will be identified in the schedule. 2. The CMAR will update the Critical Path Schedule on a regular basis thru the entire duration of the project, including close-out and pinch list completion. Document Constructability Review The CMAR shall provide recommendations on the following. a. Constructability b. Availability and Forecast of materials and labor