The project generally consists of the installation of approximately 5,100 linear feet of 8-inch DR 17 blue PVC sanitary sewer force main, combination air valves, plug valves, and related appurtenances to reroute existing main force. The project will require one connection to an existing force main at the upstream end and one connection to a separate force main on the downstream end of the project. A valve will be installed, normally closed, on the existing force main at the upstream end of the project to divert flow to the new force main. The existing force main after the valve will remain in place. The project will also include approximately 80 linear feet of DR 11 HDPE installed via horizontal directional drilling, approximately 100 linear feet of RJDIP to cross a stream, and approximately 120 linear feet of RJDIP loaded into an existing casing pipe to cross a road