BOONE STREET: This section includes a sidewalk length of approximately 420 feet at 5-feet wide, for a total of 2,100 square feet of concrete sidewalk. It includes 420 linear feet of monolithic curb pour, (10) ADA ramps with (4) ramps requiring truncated domes. General: The sidewalk will be 5-feet in width as specified. The contractor is responsible for all grade work, removal of spoils, framing and pouring sidewalk and the curb. The sidewalk must have a curb face where adjoining the edge of the street and shall be a monolithic pour. The contractor is responsible for traffic control during the entire length of the project. The contractor will backfill the sidewalk, and/or curb with topsoil and stabilize with seed and straw. Approximately half of the sidewalk in this project will be poured over existing asphalt. In areas that require excavation of soil or stone, base stone must be a minimum of 4-inches in depth compacted and grade C or grade D stone must be used. If pouring over asphalt, no more than 2 inches of compacted grade C or D stone must be used.