Specifications include, but are not limited to: 3.1 Plugging Requirements for the 3-30 State well (API 40 063 20611) 3.1.1 Fill casing from PBTD at 1600’ to surface with approximately 125 sacks Class G cement. 3.1.2 If the hole accepts less than 90% of the calculated 125 sacks required, corrective action must be taken to address bridging of the cement. 3.1.3 After 12 hours, ensure that cement has not settled before installing the marker plate. If settling has occurred, install sufficient cement to within four feet of the surface. 3.1.4 Remove all equipment and debris (see attached site photos for extent of equipment and debris on site), cut casings off four (4) feet below ground level. Weld on plate with weep hole, inscribe well location information on plate. 3.1.5 Reclaim the well site in accordance with state reclamation requirements found in ARSD 74:12:03:06. 3.1.6 Cement volumes are based on cement with 1.15 cubic feet per sack yield. Volumes must be adjusted accordingly if cement with a different yield is used.