A. Installation of new water mains and appurtenances along Old Parker Rd, Mauldin Cir, and Starsdale Cir, to include approximately: 1. 2,900 feet of 6-inch DIP Water Main; 2. 550 feet of 8-inch DIP Water Main; 3. Six (6) 6- and 8-inch Gate Valves; 4. Three (3) Fire Hydrant Assemblies; 5. 40 LF of 12-inch steel casing installed via jack and bore B. Connections to the existing water system. C. Installation of a temporary water bypass system, as needed, to maintain service to existing customers while the new water mains are installed. D. Installation of service connections from the new mains to existing water meters. This contract includes the service line to the existing meter and replacement of the existing meter box. The existing meters will not be replaced as a part of this contract.