Specifications include, but are not limited to: A. Locate underground utilities and solve any conflicts prior to excavation. B. Contact all Utility Providers and coordinate the location of their lines. C. Install and maintain Traffic Calming, Detour Signage, stakes and Limits of Disturbance. D. Identify the limits of clearing; remove, grind and dispose of trees and vegetation. E. Clear, grub and excavate upstream, downstream and to the Limits of Disturbance. F. Demolish, remove and dispose of existing Corrugated Metal Pipe (CMP) and Storm Drainage System. G. Install an Eighty (80) Foot Aluminum CMP (12 Gauge, 3” x 1”), 96” Diameter Pipe with a Concrete Head Wall/Wing Walls MST or comparable, in accordance with the Drawing Dated 4/7/20, prepared by MST Inc. Concrete Products (see Page 20 attached). H. Use caution as work area is in the Flood Zone; no fill is allowed. I. Remove and dispose of Asphalt Roadway and Concrete Curbing.