Specifications include, but are not limited to: A. The Contractor shall employ workers that are competent and properly trained to perform the required tasks. B. The Contractor shall be responsible for coordinating, scheduling and supervising all work activities to assure compliance and deadlines specified herein. All lights must be installed and working by Wednesday November 26, 2014. Lights are to be picked up by the Contractor at the Driessen Beach Park storage area. Timers shall be set to come on beginning Friday November 28, 2014 at 6pm and remain on until 2am. All Christmas Wreaths must be installed on traffic arm masts on Friday November 28, 2014 and finish with installation by Monday December 1, 2014. Christmas wreaths are to be picked up by the Contractor at the Jarvis Park storage area. Lights at Compass Rose Park shall be removed from all landscaping between January 2, 2015 and January 9, 2015. All lights are to be removed by January 15, 2015.