Specifications include, but are not limited to: Tyler Slump Repair 3.3 Mile Clear inlet of material that slumped from the draw above. End haul material to location specified by the forest officer (within 1 mile of slump location) Replace existing plastic culvert with 24” X 60’ CMP. During install compact CMP every 6” with Bucket rolling wheel tamper or compactor. Do NOT side cast any material in the draw, it all needs to be piled on the road and excess material will be end hauled. When installing new CMP maintain slope angle and dig sediment catch basin at inlet, resulting in the inlet of the pipe being 1-4” above ground. This will allow for more sediment delivery without impacting the CMP if another fail occurs. Step material down from the debris cone to the sediment catch basin. Inlet location will be flagged in pink. Place slash filter windrow 30’ on either side of the new CMP to limit cattle damage on fresh fill. Construct a ditch to the existing dip west of the CMP. Rock armor the inlet and outlet