Specifications include, but are not limited to: Main tile lines sized large enough to handle possible future expansion for the rest of the SE ¼ (total acres approximately 125 acres) if not completed on this project. Minimum 5 hp. variable flow pump located in SE corner of field (see map) or optional 7.5 hp pump if entire SE ¼ is bid also Any excavating on main line or lateral “tie in’s” require segregation and replacement of topsoil from the subsoil (no clay put back on top) Contractor obtains necessary permits if needed Permit for drainage into state highway ditch (frontage road) will be obtained by Agronomy Seed Farm If tile lines are run east/west, additional tile along west side of field (along field road) need to be installed parallel to field road Completion date dependent on weather. Needs to be completed prior to ground freezing up this fall.