1. Removal of all vegetation within Pond 1 and Pond 2, removal of vegetation along the dikes inside Pond 3 and adjacent to Pond 2, removal of vegetation along inside of Pond 4 dike and chipping and placement of removed vegetation in the defined areas at the site for vegetation disposal areas. 2. Demolition of existing pipe works, transfer structures, interconnecting piping and overflow structures and excavation and removal of sludge from Pond 1 and Pond 2 that will be placed in Pond 3. 3. Rehabilitation of Pond 1 and Pond 2 with reconstruction of internal Pond 1 and Pond 2 dikes with on site soils including all excavation, earthwork, placement, compaction and reconstruction of access roads to ponds. 4. Construction and installation of new gravity main to ponds, manholes, influent piping, transfer structures, overflow piping, plug valves and bypass piping. 5. Placement of geotextile fabric and 6 inch RSP to interior of dikes in Pond 1 and Pond 2. 6. Vegetation removal and along interior of dikes of Pond 4, and placement of material on site in designated areas.