his project involves the completion of 99 customer service lines in a new subdivision. The installation, tie-in to existing natural gas customer service lines and commissioning of approximately 1,770 linear feet of 3/4-inch polyethylene natural gas service lines and associated appurtenances. The methods of installation for the services shall be exclusively direct burial. The subdivision developer has provided the following home construction schedule: Construction to start between December 1 and December 10, 2025 5 to 6 home starts monthly for the first few months, then 4 starts per month until build out The first 6 homes are scheduled to be completed in 75 After that completions are scheduled for 95 days after start.