This project involves a mixture of overhead primary lines and underground primary lines along with transformers and switchgears. Consists of setting three Ductile Iron poles: 50/H9 approx. 4,970 lbs each. Install twenty-two, 45/2 wood poles. Install 6in Sch40 PVC combined length of approx. 2500ft. Install approx. 2500 feet combined length of 1000mcm 3 phase primary cable. Install 24 1000mcm T-Bodies. Install 7 Gang operated RLB switches. Install 1 PME-10 Switch Cabinet. Install 18 1000mcm Terminators. Install 336 ACSR combined length of approx. 20,000 feet. Install 70 336 Perform top ties. Install approx. 3,000 feet combined length of 1/0 25kv cable. Install approx. 2,000 feet combined length of 4/0 25kv cable. Install 4 –25KV 3000KVA Transformers 277/480. Install 1000mcm feeder from substation to metering cubicle. Change out existing PME-10 to metering cubicles. Install two new metering cubicles on top of existing vault. Conduits will be Stubbed outside the substation fence by MEAG Power. The contractor will be responsible for maintaining the phasing of all tie points.