This work shall consist of furnishing all labor, material, and equipment necessary to install integral curb and gutter around the cul-de-sac and south to next driveways. The Contractor shall be responsible for hauling all material waste. All work shall be in accordance with the requirements, the applicable drawings, and subject to the terms and conditions of these guidelines. Contractor shall complete all work. Contractor shall remove the existing asphalt and earth perimeter to the limits shown on Figure 2. A new 3” (6” on west side radius) rolled curb shall be installed along the perimeter of the cul-de-sac. The new curb shall follow a new radius pulled from the circle center. City surveyors will stake limits one time. The top profile of the curbs will be field determined to maintain water flow north and south.