• Preliminary Design Data Collection: Consultant team shall collect all necessary data and information for the successful completion of this project. Data may include, but not be limited to, existing site conditions, geotechnical data, utility locations/conditions, adjacent property restoration needs, utility relocation coordination and determining ADA requirements. Survey data (topography and existing utilities). • Low Impact Development Feasibility: Consultant team shall evaluate feasibility of LID techniques like pervious pavement and bioretention using the currently adopted stormwater manual. • Project Design and Specifications: Consultant team shall prepare preliminary and final engineering Plans and Specifications at the level of 30%, 90% and 100%. Consultant team shall prepare final bid document package by the Ad date outlined in the schedule. City staff shall review and provide comments after each level of effort. • Estimated Project Cost: Consultant team shall prepare an estimate of probable cost for the construction phase of the project at the 30%, 90% and 100% levels.