• Construction of a large reinforced concrete bifurcation water control structure in a canal. The work entails excavation, subbase placement and compaction, foundation preparation, concrete formwork, concrete placement, backfill, fabrication and installation of exterior galvanized metal walkway and handrails, and installation of raceways and conductors for equipment power and instrumentation. • Installation of owner-prepurchased four (4) 10-foot wide by 6-foot tall overshot steel gates and gate hoists, and installation of owner-prepurchased control panel and level sensing instruments, with installation oversight by gate manufacturer. Contractor to assist with start-up and commissioning with Owner and gate manufacturer.