The specifications listed below set forth the necessary requirements: Provide labor, material, and equipment: 1. 1 Oil Fired Boiler; 2. Brand of primary Boiler shall be Well-McLain or equivalent; 3. Beckett Oil Burner or equivalent; 4. 2 circular pumps (one being a backup); The work will consist of the following: 1. Mobilization on site; 2. Install temporary protection as needed; 3. Remove existing boiler and dispose of material; 4. Patch/Parge existing masonry (if needed); 5. Install new oil boiler; 6. Install associated plumbing, glycol, temperature gauges and expansion tank; 7. Install structural concrete grout and masonry if needed; 8. Bidder shall be responsible for obtaining all permits required and any associated costs; 9. New oil lines from boiler to concrete oil tank located outside; 10. All work must be completed by December 5, 2025