One award for all items will be made. Performance time is 754 calendar days. Estimated price range is under $15 million. Major items of work are: 8,503 LF fence removal; 3,380 LF silt fence; 51.5 Acre sprigging; 1 irrigation system; 10,488 1000-Gal irrigation water; 85,334 CY common excavation; 77,757 CY standard earthfill; 3,077 earthfill beneath RCC; 4,396 CY drainfill; 102,523 SY topsoiling; 921 LF diversions; 401.5 CY structural concrete; 65.3 CY pipe cradle concrete; 51,656 Lb. reinforcing steel; 9,238 CY roller compacted concrete; 1,684.0 Ton cementitious materials; 180 LF 42” C-301 concrete pressure pipe; 3,332 LF 6” I.D. PVC plastic pipe; 53 LF 4” I.D. PVC plastic pipe; 5,083 Ton rock riprap; 474.0 LF chain link fence; 8,429 LF barbed wire fence; 8,397 SY geotextile; and 1 Job, lump sum each for clearing and grubbing, principal spillway removal, pollution control, construction surveys, mobilization and demobilization, removal of water, 18”x18” slide gate; principal spillway metal work, contractor quality control, and conduit abandonment.