This project entails the complete procurement and installation of a Kohler model KG150 natural gas generator at the exterior of the filtration plant's shop dock. The contractor will be responsible for all tasks associated with the proper installation and operation of the generator system, including: Supply of Kohler model KG150 natural gas generator, provision of all necessary parts and installation materials, placement and mounting of the generator at the designated exterior location, running of a natural gas line from the existing supply to the generator, all necessary electrical wiring to ensure generator operation and integration with facility systems, testing and commissioning of the generator to ensure full operational readiness. Additionally, the contractor will be responsible for the development and delivery of a Standard Operating Procedure (SOP) specific to the installed system and a brief training or orientation session for facility personnel on generator use and safety.