The project includes all material, labor, and related appurtenances for complete construction as indicated on the construction drawings and in these specifications. The Work consists of the upgrade and expansion of the existing City of Cleveland Wastewater Treatment Plant from 0.75 million gallons per day (MGD) to 1.5 MGD and includes the following: The project includes upgrading the existing manual screen to an automated screen; upgrading existing pond aerators; duplex influent pumps and pump station with building; an oxidation ditch; two secondary clarifiers; flocculation tank; disc filters; UV disinfection; Parshall flume; plant drain pump station; WAS/RAS pumps; an aerobic digester with steel tank; dewatering/electrical building with rotary press; upgrades and expansion of existing control building; new chemical building; electrical work; yard piping; demolition of existing buildings, pond appurtenances, utilities, fences, and other areas as shown; SCADA system; and miscellaneous other work and improvements necessary to complete the work as described in the Contract Documents and Contract Drawings.