1. Removal of existing stone protection, ramp blocks, crushed stone and geotextile fabric 2. Stockpiling of crushed stone and riprap greater than 18” in diameter 3. Re-establish flat base for new ramp construction. 4. Build new base for ramp blocks with 2” crushed stone wrap with non-woven geotextile fabric 5. Installation of new interlocking 18’x4’x8” 6. Installation of curbing along edges of ramp blocks 7. Install two courses of 18” armor stone along curbing 8. Place remaining stockpiled rock adjacent to armor stone to ensure gradual transition to existing grade 9. Regrade gravel roadway and channels apron above the top of the ramp 10. Construct Riprap plunge pools at outfall locations shown on plan set 11. Loam and seed stormwater channels along roadway