The work consists of two primary components. The first is constructing four new sanitary pump stations; including precast concrete wet well, valve vault, meter vault, sewer force mains, gravity sewer, electrical and control equipment, paving, fencing, site lighting, site grading and restoration, equipment start-up and pump station commissioning. The second is, the installation of gravity sewer mains, manhole structures, force mains, air release valves and structures, force main cleanout structures, sewer laterals, directional drilling of force main, trench paving and site restoration, and all performance testing to construct the sewer collection system in the Route 6 and Route 118 project corridor as shown on the plans