The project involves the installation of approximately 32,000 linear feet of new gravity sewer main, connecting approximately 350 services (including both gravity and grinder pump services) and abandoning approximately 300 existing septic tanks. It also includes approximately 3,500 linear feet of new sewer force main, a triplex grinder pump lift station with a backup generator, as well as two new packaged submersible lift stations, each with a backup generator. Additionally, the project entails roughly 6,000 linear feet of low-pressure sewer main, rehabilitation of the existing main lift station inclusive of the demolition of the current dry well and the restoration of the wet well to convert to a submersible lift station.