This scope of work includes inspecting, cleaning, and refurbishment of the GE 7B “N35” non-segregated phase bus system components identified in this Scope of Work, and making repair recommendations for any as-found out of scope work items. The bus system includes the nonsegregated phase bus (Nonseg) located on top of the turning gear compartment (enclosure section) as well as the switchgear compartment and exciter compartment at the bus termination points indicated in this specification. JEA is requesting a turnkey proposal for all labor, equipment, materials and incidentals to complete the scope of work detailed below. The Contractor is to verify all quantities related to this project. This includes but not limited to all LF of bus refurbishment, bolting, hardware, insulators and connection points. JEA will provide crane support for only the bus duct enclosure section removal, placement on stands for the initial Contractor’s inspection, load/offload transport for offsite refurbishment and re-installation. Daily meetings with the Contractor shall be completed with the JEA PM and/or Engineer to go over any safety issues, discovery work, project status, and project schedule.