This project in general (approximately 3,775 linear feet in length) includes but is not limited to furnishing all labor, materials, equipment and other as included items necessary for the completion of the following: • Installation of approximately 4,100’ of 10” to 60” storm sewer; • Installation of approximately 550’ of 6” to 18” sanitary sewer; • Installation of approximately 3,500’ of 4” to 8” water main; • Approximately 2,700’ of 8” to 15” sanitary sewer lining; • Approximately 7,265 SY of pavement removal; • Approximately 5,685 SY of pavement patching; • Approximately 1,580 SY of pavement reconstruction; • Approximately 9,750 SY pavement surface milling; • Approximately 2,375’ of curb and gutter removal and replacement; • Approximately 8,950 sq. ft. of sidewalk removal and replacement; • Removal and/or abandonment of existing water and sewer mains; • Water and sewer main adjustments; • Water and sanitary service-re-establishment; • Parkway restoration and other miscellaneous items of work in accordance with the Contract Plans and Specifications.