The Owner will pre-purchase equipment and assign it to the awarded Contractor to expedite delivery and installation. The Contractor must review shop drawings to ensure all necessary labor and materials are included for installation. The Contractor is fully responsible for coordinating delivery, receiving, unloading, installation, and system integration as if they had purchased the equipment directly. This includes rigging, setting, connecting, starting, testing, and maintaining the equipment per manufacturer guidelines until project acceptance. All work must comply with the drawings and relevant specifications. Upon completion, the Contractor must compile shop drawings, O&M manuals, and part lists into the project documentation.