Contract #1 (Materials) consists of, but is not limited to the following major elements: See Section 00300 of specifications for detailed materials breakdown. Contract #2 (Construction) will consist of all of the construction work as itemized in Section 00301. All work associated with Contract #2 (Construction) is funded by GEFA and shall be subjected to DavisBacon and all Federal Requirements. Contract #2 (Construction) consists of, but is not limited to the following major elements: Construction of approximately 6,305 L.F. of 12-inch PVC waterline 23,414 L.F. of 8-inch PVC waterline, 12,086 L.F. of 6-inch PVC waterline, 1,826 L.F. of 2-inch PVC waterline, 120 L.F. of 12-inch freebore, 695 L.F. of 8-inch freebore, 667 L.F. of 6-inch freebore, 90 L.F. of 16-inch steel casing with 8- inch DIP jack and bore, 41 each fire hydrant assemblies, (4) 12-inch gate valves, (24) 8-inch gate valves, (23) 6-inch gate valves, (3) 2” Line termination with flush hydrant assembly, approximately 200 service connections and related appurtenances.