Inlet protection 25 EA \ Remove concrete curb and gutter 920 LF \ Remove concrete sidewalk 5,800 SF \ Remove concrete driveway 1,680 SF \ Excavation below subgrade 729 CY \ Pulverize asphalt pavement 8,300 SY \ Pavement sawing 690 LF \ Concrete curb and gutter 920 LF \ Concrete sidewalk 5,805 SF \ Detectable warning field 190 SF \ Concrete driveway approach 1,680 SF \ Base aggregate dense 1,680 TON \ HMA pavement 2,900 TON \ Sanitary manhole chimney repair/rebuild 7 EA \ Storm structure chimney repair/rebuild 19 EA \ Water main 1,270 LF \ Hydrant 3 EA \ Gate valve and box 13 EA \ Corporation stop 10 EA \ Connect to existing service 10 EA \ HDPE water service 245 LF \ Pavement markings 7,110 LF \ Traffic control 1 LS \ Restoration (topsoil and hydroseed) 1 LS \ This is a unit price contract.