1. The City of Ocala requires the services of an experienced contractor to complete the construction of Terminal Apron Rehab at the Ocala International Airport (OCF) 2. Scope of the project consists of the removal of approximately 27 pavement tie-downs and 8” milling of 16,364 square yards of the existing apron area. This will be followed by an overlay of 6 inches of Hot Mix Asphalt (HMA) Pavement, leveling Course with PG 76-22, totaling approximately 3,685 tons, and a final 2-inch overlay of Fuel Resistance Asphalt Mix Pavement with PG 88-22 FR, totaling approximately 1,845 tons. Additionally, the scope includes the installation of two new underground mini hatch pit systems and related electrical work, which will require the placement of underground conduits. Pavement markings will also be applied throughout the area. 3. Furthermore, the project includes the milling of 2 inches of existing asphalt in front of the terminal building, covering an area of approximately 2,240 square yards. This will be followed by an overlay of 2 inches of FDOT Superpave SP 12.5 asphalt concrete with PG 67-22, totaling approximately 255 tons. Electrical work, installation of underground conduits, and pavement marking will also be carried out to complete the area. 4. Major Items of Construction are as follows: • Tie-Down Removal • Trench Excavation • 8” Asphalt Pavement Milling • Compact Subbase • 2” Asphalt Mix (P-404) • 2” Superpave Asphalt (SP 12.5) • 6” Asphalt Mix (P-403) • Underground Conduit Work • Pavement Marking • Underground Mini Hatch Pit System • Grout fill tie-down removals • Underground Counterpoise 5. Badging of individuals in supervisory positions will be required. Allow 2 hours for the badging process. There is no cost for the badges. 6. This is a grant funded project.