SUMMARY OF WORK a. The Work of this project provides for the furnishing of all labor, materials, appliances, tools, equipment and plant, and the performing of all Work in accordance with these specifications and drawings, with exception of work that is expressly and specifically not included in the project. b. The project consists of one (1) contract: BNIA Airfield Pavement Maintenance 2025/2026. The project will be implemented under two (2) separate Notices to Proceed (NTP-1 and NTP-2) in two (2) contract years as set forth in the Contract Documents. c. The Work shall include but not limited to: General Elements 1. Airport Pavement Maintenance: Conducted over two contract years (2025 & 2026), with separate Notices to Proceed (NTP-1 & NTP-2). 2. Contract Year Assignments: Work assignments align with unit bid prices and fiscal year budgets. The Authority may adjust quantities based on funding. Landside Work Elements 1. Pavement Rehabilitation: Includes bituminous mill/overlay, full-depth repairs, crack sealing, and drainage inlet/manhole rehabilitation. 2. 251N Cayuga Rd Reconstruction: Full-depth pavement replacement, drainage system upgrades, and installation of new pavement, curbs, and markings. Airside Work Elements 1. Pavement Reconstruction: Full-depth asphalt/concrete replacement, drainage upgrades, subbase stabilization, and new pavement installation. 2. Glycol Trench Drain Work: Includes pavement removal, structural concrete reconstruction, drainage system adjustments, and pavement joint sealing Refer to the Project Manual and Contract Drawings for detailed and further information.