1. Mobilization LS 1 $_________________ $_______________ 2. Remove existing 6” concrete panels, including saw cutting and disposal SF 51,000 $_________________ $_______________ 3. 6” concrete pavement. Including subgrade preparation, pavement joint and sealing. SF 51,000 $_________________ $_______________ 4. Remove existing 4” concrete sidewalk SF 1,600 $_________________ $_________________ 5. 4” concrete sidewalk. Including headers, dowels, expansion joints, placement of 2” sand base, restoration and backfill using topsoil SF 1,600 $_________________ $_________________ 6. 8” cement stabilized base SF 51,000 $_________________ $_______________ 7. 6” curb FT 3,920 $_________________ $_______________ 8. Restore type C inlet LS 1 $_________________ $_______________ 9. Restore pavement markings LS 1 $_________________ $_______________ 10. Adjust Manhole/Valve EA 1 $_________________ $_______________ 11. Traffic Control LS 1